McKimmies Rd

Ongoing - August 2027
Bundoora, VIC
TAV Bundoora Pty Ltd & New Urban Projects Pty Ltd
Sectors
Landfill

We have been tasked with preparing a site for future residential and industrial development by conducting bulk earthworks and geotechnical remediation.

Consisting of two parts, reactivating existing landfill facilities to import and stockpile enough Fill Material for 250,000 compacted cubic meters, and then excavating and placing this material, alongside importing additional fill material for geotechnical remediation.

Our scope of work included:

  • sourcing, importing and stockpiling fill material
  • excavation and placement of stockpiled fill
  • geotechnical remediation
  • installation of soil wicks
  • gas extraction systems
  • groundwater collection pipes

 

Noteworthy achievements include installing 1,709 km of wicks in challenging conditions, constructing a wastewater treatment plant, and efficiently stockpiling material. Additionally, the project innovatively utilises material from major government projects for engineered fill, optimising space and efficiency.